Estimate cut volume, haul-off truck loads, trench and backfill quantities, and grading slope and fill, including soil swell and compaction.

Quick answer: excavation volume (bank yd³) = L × W × D (ft) ÷ 27. Multiply by a swell factor (about 1.25 for common earth) for the loose volume trucks haul away. For drainage, the IRC requires grade to fall at least 6 in within the first 10 ft from a foundation.

Bank, loose, and compacted volume

Soil in the ground ("bank" volume) expands when dug ("loose" volume) and shrinks when compacted. That is why haul-off quantities are larger than the hole, and why fill for a low spot needs more than its measured volume.

  • Swell: common earth swells roughly 23–27% when excavated, clay about 22–25%, and sand and gravel about 10–12%.
  • Shrink: compacted fill typically needs 10–25% more loose material than the finished volume.

Grading for drainage

Good grading moves water away from buildings. Measure the existing fall with a string line and line level, compare it with the target slope, and use the grading & slope calculator to work out the drop and the fill or cut volume. Driveway materials and paving are covered in the driveways & paving calculators.

Typical soil swell factors

Typical soil swell factors
MaterialApprox. swell when excavatedLoose yd³ per bank yd³
Sand / gravel10–15%1.10–1.15
Common earth / loam20–30%1.20–1.30
Clay22–25%1.22–1.25
Topsoilabout 43%1.43
Rock (blasted)50–65%1.50–1.65

Full table by soil type, with bank and loose weights: soil swell factor table.

Frequently asked questions

How do I calculate how much dirt to remove?

Multiply length × width × depth in feet and divide by 27 for bank cubic yards, then multiply by the swell factor (about 1.25 for common soil) to get the loose volume trucks will haul.

How many cubic yards fit in a dump truck?

A standard tandem-axle dump truck hauls roughly 10–14 loose cubic yards, and a single-axle truck about 5–7. Weight limits can cap loads of wet or dense material first.

How much should the ground slope away from a house?

The International Residential Code (R401.3) requires the grade to fall at least 6 inches within the first 10 feet from the foundation, which is a 5% slope. Where lot lines or walls prevent that, swales or drains are used instead.