Riprap Calculator
Measure width along the slope face, not the flat plan distance.
Quick answer: riprap tons = area (ft²) × layer thickness (ft) ÷ 27 × (1 + overfill) × about 1.5 tons/yd³. A 50 ft × 8 ft bank with 9 in median stone placed 18 in thick is 22.2 yd³; with 10% overfill that is 24.4 yd³, or about 36.7 tons, over 460 ft² of fabric.
Estimate rock for shoreline and stream-bank protection, drainage ditches, and culvert outlets. Pick a stone size and the tool sets a layer about twice the median stone diameter, then returns tons, cubic yards, truck loads, and the filter fabric to go underneath.
Measure width along the slope face, not the flat plan distance.
Riprap is sized by its median stone diameter, called D50: half the stones by weight are larger than D50 and half are smaller. The layer has to be thick enough for stones to interlock, so design guides commonly set thickness at 1.5 to 2 times D50, and never less than the largest stone (D100). Once you have a thickness, the quantity is a simple area × thickness volume converted to tons.
A 30 ft stretch of pond bank, 6 ft measured down the slope, protected with 4–8 in stone (D50 ≈ 6 in) placed 12 in thick:
Net quantities with no overfill. Tons shown at 1.4, 1.5, and 1.6 tons per placed yd³ to bracket typical rock densities.
| Layer thickness | Fits D50 of about | yd³ per 100 ft² | Tons at 1.4 | Tons at 1.5 | Tons at 1.6 |
|---|---|---|---|---|---|
| 12 in | 6 in | 3.70 | 5.19 | 5.56 | 5.93 |
| 18 in | 9 in | 5.56 | 7.78 | 8.33 | 8.89 |
| 24 in | 12 in | 7.41 | 10.37 | 11.11 | 11.85 |
| 30 in | 15 in | 9.26 | 12.96 | 13.89 | 14.81 |
| 36 in | 18 in | 11.11 | 15.56 | 16.67 | 17.78 |
State highway departments publish their own riprap classes (Class I, II, Type A, B, and so on) with different gradations. When a plan names a class, use that agency's D50 and thickness.
Multiply the slope area (length × width measured along the face) by the layer thickness in feet, divide by 27 for cubic yards, and multiply by about 1.5 tons per yard. A 50 × 8 ft bank with an 18 inch layer is 22.2 cubic yards, about 36.7 tons with 10% overfill.
Riprap is usually placed at 1.5 to 2 times the median stone size (D50), and at least as thick as the largest stones. For 6–12 inch stone with a D50 near 9 inches, that means a layer about 14 to 18 inches thick. Follow your permit or engineer when one specifies thickness.
Placed riprap typically weighs about 1.4 to 1.6 tons per cubic yard. Solid rock is much heavier, but riprap has 30 to 40 percent voids between stones. Granite and dense limestone sit at the high end; ask your quarry for its figure.
Yes, in almost all cases. A geotextile or gravel filter layer stops water from washing soil out through the gaps between stones. Plan fabric equal to the slope area plus 10 to 20 percent for seam overlaps and anchoring at the top and toe.
Stone size depends on flow velocity, wave action, and slope. Small ditches and gentle pond edges often use 4–8 inch stone, while stream banks and culvert outlets with faster water commonly need 9–18 inch or larger stone. For channels and outlets, use the size from your plans or an engineer.
How we built this calculator: results use the standard volume, area, and coverage formulas shown on this page, with typical U.S. material densities, bag yields, and waste factors that you can override. Written and checked by the YardsCalculator editorial team. Last reviewed: October 2026.