Slab Bid & Quote Estimator

Concrete Slab Quote Calculator

Turn slab dimensions, concrete price, labor, and other job costs into a customer quote with markup. This concrete slab quote calculator shows base cost, markup amount, and final price.

Quick answer: slab quote = (cubic yards × $/yd³ + labor + other costs) × (1 + markup%). A 24 × 24 ft slab 5 in thick is 8.89 yd³; at $155/yd³ plus $2,200 labor and $600 other costs, base cost is $4,177.78 and a 20% markup gives $5,013.33.

  • Markup-ready quotes
  • Realtime results
  • Pre-bid friendly
  • Mobile friendly

Slab Diagram

Plan View (Length × Width) L: 24 ft W: 24 ft Side View (Thickness) T: 5 in

Slab Quote Builder

Enter job costs and markup — quote updates instantly

Quote Inputs

Final Quote—
Base Cost—
Concrete Yards—
Markup Value—

Example Slab Quotes

Tap a preset to load dimensions—then adjust labor, other costs, and markup.

10×10 Patio Slab

Small patio bid: 10 ft × 10 ft × 4 in.

Garage Slab

Garage floor quote: 24 ft × 24 ft × 6 in.

Driveway Slab

Drive pour: 20 ft × 40 ft × 5 in.

Sidewalk Pour

Walk path: 4 ft × 50 ft × 4 in.

How to build a concrete slab quote

A slab quote starts from your own cost — concrete, labor, and everything else the job consumes — and then adds markup to cover overhead and profit. This calculator works out the concrete volume from the slab size, prices it at your delivered cost per cubic yard, adds a labor total and an "other costs" total, and applies one markup percentage to the whole base cost.

Quote = (yd³ × $/yd³ + labor + other) × (1 + markup%)yd³ = length × width × (thickness in ÷ 12) ÷ 27 — no waste is added to the yards
  1. Enter slab length, width, and thickness. The calculator converts them to cubic yards.
  2. Enter your concrete price per cubic yard as delivered, including any fuel or environmental surcharges your plant charges.
  3. Enter the labor total for the crew — prep, forming, placing, finishing, and stripping — as a single dollar amount.
  4. Enter other costs: gravel base, forms, rebar or mesh, vapor barrier, pump or buggy rental, saw cutting, curing compound, permits, and dumpster or haul-off.
  5. Set markup and read the final quote, base cost, and markup amount.

Worked example: default 24 × 24 ft slab, 5 in thick

  • Concrete: 24 × 24 × (5 ÷ 12) = 240 cu ft ÷ 27 = 8.89 yd³ × $155 = $1,377.78
  • Base cost: $1,377.78 + $2,200 labor + $600 other = $4,177.78
  • Markup at 20%: $4,177.78 × 0.20 = $835.56
  • Final quote: $5,013.33, or about $8.70 per sq ft over 576 sq ft

Because the yards have no waste built in, order and price about 5–10% extra concrete for subgrade variation and spillage. You can cover that by adding the extra yards' cost to Other Costs — for this slab, 8% more is about 0.71 yd³, or $110 at $155 per yard.

Markup vs. profit margin

Markup is a percentage of cost; margin is a percentage of the selling price. The calculator's field is markup. Use this table to hit a target margin.

Markup percentage and the resulting gross margin percentage
Markup on costGross margin on quoteQuote on $4,177.78 base cost
10%9.1%$4,595.56
15%13.0%$4,804.44
20%16.7%$5,013.33
25%20.0%$5,222.22
30%23.1%$5,431.11
40%28.6%$5,848.89
50%33.3%$6,266.67

Concrete yards for common slab sizes

Net volume (no waste) and concrete cost at the default $155 per cubic yard.

Cubic yards and concrete material cost for common slab sizes
SlabThicknessCubic yardsConcrete at $155/yd³
10 × 10 ft patio4 in1.23$191
4 × 50 ft sidewalk4 in2.47$383
24 × 24 ft garage4 in7.11$1,102
24 × 24 ft garage6 in10.67$1,653
20 × 40 ft driveway5 in12.35$1,914

Slab quoting mistakes to avoid

  • Confusing markup with margin. A 20% markup yields only a 16.7% margin. If your business plan calls for a 20% margin, you need a 25% markup.
  • Pricing net yards only. The calculator's yards are exact. Add 5–10% overage to what you order and price, or you pay for the extra concrete out of profit.
  • Missing short-load fees. Many ready-mix plants add a charge for small loads, and waiting time beyond the allowed unload window is billed too. Put both in Other Costs.
  • Leaving out site prep. Excavation, compacted gravel base, and haul-off of spoils can cost as much as the concrete on small jobs.
  • One quote for every thickness. Going from 4 in to 6 in adds 50% more concrete. Confirm the thickness the job, plans, or local code require before quoting.
  • No expiry date. Concrete prices change, so state how long the quote is valid and what is excluded.

Cost vs quote vs floor estimate

  • This page (Quote): Markup on labor, other costs, and material for a bid total.
  • Concrete cost calculator: Expense budget with delivery, rebar, and finish lines.
  • Floor cost per sq ft: Fast sf-based labor and rebar pricing.

Slab quote FAQ

How do you calculate a concrete slab quote?

Add the concrete cost (cubic yards × price per yard), the labor total, and other job costs to get a base cost, then multiply by 1 plus your markup. A 24 × 24 ft, 5 in slab at $155 per yard with $2,200 labor, $600 other costs, and 20% markup comes to $5,013.33.

What is the difference between markup and margin on a concrete job?

Markup is calculated on your cost, while margin is the share of the selling price that is profit. A 20% markup on $4,177.78 adds $835.56, which is 16.7% of the $5,013.33 quote; a 25% markup is needed for a 20% margin.

What is the difference between a slab cost and a slab quote?

Cost is what the job takes to build — concrete, labor, materials, and equipment. The quote is the price the customer pays, which adds markup to cover overhead such as insurance, vehicles, and office time, plus profit.

Does this slab quote calculator include waste concrete?

No. It prices the exact cubic yards for the slab dimensions. Add 5 to 10 percent overage by including the extra yards' cost in Other Costs; for a 24 × 24 ft, 5 in slab, 8% extra is about 0.71 yards, or $110 at $155 per yard.

What should be included in other costs on a slab bid?

Typical items are gravel base, form lumber or rental forms, rebar or wire mesh, vapor barrier, pump or concrete buggy rental, saw cutting, curing compound, permits, short-load fees, and haul-off of excavated soil. List them separately on your worksheet so nothing is missed.

How we built this calculator: results use the standard volume, area, and coverage formulas shown on this page, with typical U.S. material densities, bag yields, and waste factors that you can override. Written and checked by the YardsCalculator editorial team. Last reviewed: October 2026.